Building and Support Services Section
Fast Track Building Permit Process
|

|
What is the Fast Track Building Permit
Service?
The Fast Track Building Permit Process
provides you with the staff who will work closely with you from the
application stage until the Town issues the permit, generally in 3 to 5
business days, as opposed to the standard 10 days.
|
What projects qualify for the Fast Track
Building Permit Process?
Subject to the discretion of Building and
Support Services Section staff the following projects may qualify for the Fast
Track Building Permit service:
▪ basic decks
▪ small detached garages, carports and sheds
▪ demolition permits
▪ installing or converting to municipal water
service or sanitary sewer
▪ making minor interior alterations including
basement finishes
▪ changing heating or ventilation systems
(except geo-thermal systems)
▪ making new or enlarged exterior wall
openings (windows/doors)
▪ installing wood burning appliances (stoves,
fireplaces)
▪ installing new plumbing fixtures/finishing
roughed in plumbing
When is this service available?
The Fast Track Building Permit Service is
available during regular business hours at the Town of Caledon. Please note that if we receive your
application after 2:00 p.m. we will not start the process until the following
day.
Step by Step Guide
Step 1:
Verification of external agency or internal department approvals
Applicant verifies with the Town if their
application requires any external agency or internal department approvals. If yes, then approval from the external
agency or internal department is required to be provided prior to
submission. If no, then proceed to
submission process.
Step 2:
Submission process
Applicant submits the following documents:
▪ completed permit application form “Permit to
Construct or Demolish”
▪ Schedule 1:
Designer Information
▪ external agency or internal department
approvals (if applicable)
▪ 2 sets of plans as required by the Building By-law
drawn to scale
▪ applicable permit fee
Step 3:
Review process
Application is reviewed by the Counter
Technician to determine compliance with the Ontario Building Code and Zoning By-law
within 3 – 5 business days.
Step 4:
Notification
Applicant is notified within 3 – 5 business
days that their permit is ready for issuance or whether we require additional
information to complete the review.
Choose your application package
Click on a package below that suits your
project, complete the information and submit to the Town of Caledon Building
and Support Services Section.
Accessory
Buildings Masonry
Fireplace & Chimney
Basement
Finish New
Municipal Services
Changes
to HVAC System New
or Enlarged Openings
Decks New
Plumbing
Demolition Woodstove
& Chimney